PH&ME DEPT - STATUS OF SC - ST COMPONENT WORKS IN AP
S.No Fund Amount allocated
(Rs in lakhs)
Amount Released
(Rs in lakhs)
Amount spent
(Rs in lakhs)
STAGE OF WORK TOTAL WORKS TAKEN UP BILLS PENDING
Estimation, AS
& TS Stage
Tendering Stage Not started stage In-Progress stage Completed works
Number Value
in lakhs"
Number Value
in lakhs
Number Value
in lakhs
Number Value
in lakhs
Number Value
in lakhs
NUMBER VALUE NUMBER BILLS
PENDING
in lakhs
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
2013-14
1 SCSP 8546.86 6022.87 5118.58 36 196.72 2 27.81 31 128.71 18 125 1102 7504.91 1189 7983.15 2 14.42
2 TSP 567.48 273.68 343.17 7 41.26 0 0 7 16.99 1 .6 121 389.37 136 448.22 8 13.53
2014-15
1 SCSP 1594.29 1117.32 1062.97 23 53.14 2 15.95 7 37.82 2 10.2 222 1061.57 256 1178.68 1 5.7
2 TSP 304.54 12.19 302.31 0 0 0 0 0 0 0 0 26 304.19 26 304.19 0 0
2015-16
1 SCSP 32913.11 26836.97 6269.08 222 1905.66 453 3983.43 199 2053.36 748 12626.76 1790 15559.692 3412 36128.902 580 4952.29
2 TSP 482.98 463.82 26.85 6 23 0 0 0 0 20 223.8 23 167.4 49 414.2 0 0
2016-17
1 SCSP 75981.53 3619.16 1449.79 2176 35385.43 1239 21549.06 369 4150.28 756 8755.48 857 4196.47 5397 74036.72 327 3252.66
2 TSP 18774.86 454.85 237.09 491 8376.63 230 3672.55 92 1155.73 31 225.35 26 140.6 870 13570.86 0 0
Total 139166 38801 14810 2961 23186 1926 29249 705 7543 1576 21967 4167 29324 11335 134065 918 8239