Excel Download Excel Download

Financial Year District Fund

<
District Sl.no City Financial Year Fund Amount Allocated
(Rs in lakhs)
Amount Released
(Rs in lakhs)
Amount Spent
(Rs in lakhs)
Stage of work Total Works
Taken Up
Bills Pending REASONS FOR DELAY IN SANCTIONING/ TENDERING/ NOT STARTING / SLOW PROGRESS/ BILLS PENDING
Estimation,AS & TS Stage Tendering Stage Not started stage In progress stage Completed works NUMBER VALUE Number TOTAL AMOUNT OF BILLS PENDING
in lakhs
Number Value
(in Lakhs)
Number Value
(in Lakhs)
Number Value
(in Lakhs)
Number Value
(in Lakhs)
Number Value
(in Lakhs)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Anantapur 1 Ananthapur M.Corp 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 2 Ananthapur M.Corp 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 3 Ananthapur M.Corp 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 4 Ananthapur M.Corp 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 5 Ananthapur M.Corp 2015-16 SCSP 426.8 253.12 0 0 0 0 0 0 0 37 363.11 13 63.69 50 426.8 0 0 -
Anantapur 6 Ananthapur M.Corp 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 7 Ananthapur M.Corp 2016-17 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 8 Ananthapur M.Corp 2016-17 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 9 Dharmavaram 2013-14 SCSP 30 30 30 0 0 0 0 0 0 0 0 14 30 14 30 0 0 -
Anantapur 10 Dharmavaram 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 11 Dharmavaram 2014-15 SCSP 28.88 28.88 28.88 0 0 0 0 0 0 0 0 10 28.88 10 28.88 0 0 -
Anantapur 12 Dharmavaram 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 13 Dharmavaram 2015-16 SCSP 150.71 110.08 0 0 0 0 0 5 16.8 2 17.5 24 116.412 31 150.712 24 116.412 -
Anantapur 14 Dharmavaram 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 15 Dharmavaram 2016-17 SCSP 34 34 0 0 0 10 34 0 0 0 0 0 0 10 34 0 0 Amount allocated but not sanctioned-
Anantapur 16 Dharmavaram 2016-17 TSP 15 15 0 1 3.1 2 11.9 0 0 0 0 0 0 3 15 0 0 Amount allocated but not sanctioned-
Anantapur 17 Gooty 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 18 Gooty 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 19 Gooty 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 20 Gooty 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 21 Gooty 2015-16 SCSP 170.11 170.11 0 21 170.11 0 0 0 0 0 0 0 0 21 170.11 0 0 Estimates under preparation for Technical Sanction
Anantapur 22 Gooty 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 23 Gooty 2016-17 SCSP 100.88 0 0 1 50 0 0 6 50.88 0 0 0 0 7 100.88 0 0 For 1 work Rs.50.00 Lakhs Preparation of Detailed Project Report on Comprehensive Storm Water Drainage has been entrusted to CIST Infrastructure, Vijayawada for the work proposed under SCSP and a letter addressed to the CIST Infrastructure, Vijayawada for submission of DPR immediately.
Anantapur 24 Gooty 2016-17 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 25 Guntakal 2013-14 SCSP 186.56 141.4 89.91 0 0 0 0 2 14.8 1 6 10 89.91 13 110.71 0 0 -
Anantapur 26 Guntakal 2013-14 TSP 3.2 3.2 2.79 0 0 0 0 0 0 0 0 3 2.79 3 2.79 0 0 -
Anantapur 27 Guntakal 2014-15 SCSP 12.38 12.38 12.38 0 0 0 0 0 0 0 0 3 12.38 3 12.38 0 0 -
Anantapur 28 Guntakal 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 29 Guntakal 2015-16 SCSP 298.58 223.93 8 0 0 0 0 6 58 23 222.58 2 18 31 298.58 1 8 -
Anantapur 30 Guntakal 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 31 Guntakal 2016-17 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 32 Guntakal 2016-17 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 33 Hindupur 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 34 Hindupur 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 35 Hindupur 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 36 Hindupur 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 37 Hindupur 2015-16 SCSP 690.79 504.56 0 0 0 0 0 42 356.18 6 40 2 10 50 406.18 0 0 47 works for takenup with estimate cost of Rs.406.18 lakhs and remaining works takenup shortly.
Anantapur 38 Hindupur 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 39 Hindupur 2016-17 SCSP 410 0 0 48 410 0 0 0 0 0 0 0 0 48 410 0 0 A/s is be obtained from the Municipal Council on 04.02.2016 for 48 works and tenders will be called shortly
Anantapur 40 Hindupur 2016-17 TSP 49 0 0 6 49 0 0 0 0 0 0 0 0 6 49 0 0 A/s is obtained from the Municipal Council on 04.02.2016 and tenders will be called shortly
Anantapur 41 Kadiri 2013-14 SCSP 6 6 6 0 0 0 0 0 0 0 0 3 6 3 6 0 0 -
Anantapur 42 Kadiri 2013-14 TSP 4 4 6 0 0 0 0 0 0 0 0 2 4 2 4 0 0 -
Anantapur 43 Kadiri 2014-15 SCSP 4 4 4 0 0 0 0 0 0 0 0 2 4 2 4 0 0 -
Anantapur 44 Kadiri 2014-15 TSP 5.5 5.5 5.5 0 0 0 0 0 0 0 0 2 5.5 2 5.5 0 0 -
Anantapur 45 Kadiri 2015-16 SCSP 46.81 34.19 10 13 27.76 0 0 0 0 0 0 5 10 18 37.76 0 0 -
Anantapur 46 Kadiri 2015-16 TSP 6 6 6 0 0 0 0 0 0 0 0 3 6 3 6 0 0 -
Anantapur 47 Kadiri 2016-17 SCSP 244 0 0 13 27.76 0 0 0 0 0 0 0 0 13 27.76 0 0 -
Anantapur 48 Kadiri 2016-17 TSP 136 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 49 Kalyandurgam 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 50 Kalyandurgam 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 51 Kalyandurgam 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 52 Kalyandurgam 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 53 Kalyandurgam 2015-16 SCSP 63.66 8.74 0 0 0 14 63.66 0 0 0 0 0 0 14 63.66 0 0 Technical bid stage.
Anantapur 54 Kalyandurgam 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 55 Kalyandurgam 2016-17 SCSP 195 0 0 33 157.25 0 0 0 0 5 37.75 0 0 38 195 0 0 Out 5 works 1 work in curing stage balance 4 no of works are in progress. For balance 33 works Estimates submitted for technical sanction.
Anantapur 56 Kalyandurgam 2016-17 TSP 140.62 0 0 28 141 0 0 0 0 0 0 0 0 28 141 0 0 Estimates submitted for Technical Sanction.
Anantapur 57 Madakasira 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 58 Madakasira 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 59 Madakasira 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 60 Madakasira 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 61 Madakasira 2015-16 SCSP 64.09 64.09 0 0 0 10 64.09 0 0 0 0 0 0 10 64.09 0 0 Tenders to be Published.
Anantapur 62 Madakasira 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 63 Madakasira 2016-17 SCSP 100 0 0 9 100 0 0 0 0 0 0 0 0 9 100 0 0 Awaited for Council Approval
Anantapur 64 Madakasira 2016-17 TSP 50 0 0 6 50 0 0 0 0 0 0 0 0 6 50 0 0 -
Anantapur 65 Paamadi 2013-14 SCSP 20.39 20.39 13.7 0 0 0 0 3 6.69 0 0 7 13.7 10 20.39 0 0 -
Anantapur 66 Paamadi 2013-14 TSP 0.29 0.08 0 0 0 0 0 2 0.29 0 0 0 0 2 0.29 0 0 -
Anantapur 67 Paamadi 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 68 Paamadi 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 69 Paamadi 2015-16 SCSP 154.17 91.43 0 12 117.05 3 19.95 0 0 3 16.17 1 1 19 154.17 1 1 -
Anantapur 70 Paamadi 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 71 Paamadi 2016-17 SCSP 100 0 0 28 100 0 0 0 0 0 0 0 0 28 100 0 0 -
Anantapur 72 Paamadi 2016-17 TSP 41 0 0 5 41 0 0 0 0 0 0 0 0 5 41 0 0 -
Anantapur 73 Puttaparthy 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 74 Puttaparthy 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 75 Puttaparthy 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 76 Puttaparthy 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 77 Puttaparthy 2015-16 SCSP 114.45 67.88 0 0 0 7 22.38 0 0 6 45.5 0 0 13 67.88 0 0 6 Works Under process-
Anantapur 78 Puttaparthy 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 79 Puttaparthy 2016-17 SCSP 100 0 0 13 100 0 0 0 0 0 0 0 0 13 100 0 0 -
Anantapur 80 Puttaparthy 2016-17 TSP 77 0 0 12 77 0 0 0 0 0 0 0 0 12 77 0 0 -
Anantapur 81 Rayadurg 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 82 Rayadurg 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 83 Rayadurg 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 84 Rayadurg 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 85 Rayadurg 2015-16 SCSP 246.69 180.18 0 6 146 9 98.69 0 0 0 0 0 0 15 244.69 0 0 -
Anantapur 86 Rayadurg 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 87 Rayadurg 2016-17 SCSP 304 0 0 35 304 0 0 0 0 0 0 0 0 35 304 0 0 -
Anantapur 88 Rayadurg 2016-17 TSP 188.5 0 0 31 189 0 0 0 0 0 0 0 0 31 189 0 0 -
Anantapur 89 Tadipatri 2013-14 SCSP 82.54 82.54 82.54 0 0 0 0 0 0 0 0 5 82.54 5 82.54 0 0 -
Anantapur 90 Tadipatri 2013-14 TSP 13.64 13.64 13.64 0 0 0 0 0 0 0 0 5 13.64 5 13.64 0 0 -
Anantapur 91 Tadipatri 2014-15 SCSP 12.48 12.48 12.48 0 0 0 0 0 0 0 0 5 12.48 5 12.48 0 0 -
Anantapur 92 Tadipatri 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 93 Tadipatri 2015-16 SCSP 499.03 364.49 0 21 200.61 18 172.24 0 0 18 95.05 4 32 61 499.9 4 32 -
Anantapur 94 Tadipatri 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 95 Tadipatri 2016-17 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Anantapur 96 Tadipatri 2016-17 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 97 Chittoor M.Corp 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 98 Chittoor M.Corp 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 99 Chittoor M.Corp 2014-15 SCSP 69.78 69.78 69.78 0 0 0 0 0 0 0 0 13 69.78 13 69.78 0 0 -
Chittoor 100 Chittoor M.Corp 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 101 Chittoor M.Corp 2015-16 SCSP 212.31 212.31 31.72 0 0 0 0 1 5 16 74.74 26 131.86 43 211.6 6 24.26 Bill to be submitted to PAO Rs.76.00 Lakhs (14 Nos)
Chittoor 102 Chittoor M.Corp 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 103 Chittoor M.Corp 2016-17 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 CR obtained for Rs.212.00 Lakhs (52) Nos. 2. Works identified and ready for Rs.3800.00 lakhs
Chittoor 104 Chittoor M.Corp 2016-17 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 105 Madanapalle 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 106 Madanapalle 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 107 Madanapalle 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 108 Madanapalle 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 109 Madanapalle 2015-16 SCSP 338 200.5 0 0 0 0 0 0 0 30 200.5 0 0 30 200.5 0 0 pricebid has been opened and sent to EE (PH) Tirupathi for tender opinion, inanticipation orders have been taken from CP , work orders have to be issued
Chittoor 110 Madanapalle 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 111 Madanapalle 2016-17 SCSP 394 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Council Resolution has been obtained on 30-01-2017 and sent for technical sanction
Chittoor 112 Madanapalle 2016-17 TSP 175 0 0 23 175 0 0 0 0 0 0 0 0 23 175 0 0 Council Resolution has been obtained on 30-01-2017 and sent for technical sanction-
Chittoor 113 Nagari 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 114 Nagari 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 115 Nagari 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 116 Nagari 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 117 Nagari 2015-16 SCSP 50 29.65 0 0 0 10 29.65 0 0 0 0 0 0 10 29.65 0 0 Tender called for 10 works in e procurement. Bid document to be opened on 31.01.2017, 5.00PM
Chittoor 118 Nagari 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 119 Nagari 2016-17 SCSP 30 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 120 Nagari 2016-17 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 121 Palamaneru 2013-14 SCSP 23.65 23.65 23.65 0 0 0 0 0 0 0 0 10 10 10 10 0 0 -
Chittoor 122 Palamaneru 2013-14 TSP 0.85 0.85 0.85 0 0 0 0 0 0 0 0 1 0.85 1 0.85 0 0 -
Chittoor 123 Palamaneru 2014-15 SCSP 33.1 23.5 23.5 0 0 0 0 0 0 0 0 8 23.5 8 23.5 0 0 -
Chittoor 124 Palamaneru 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 125 Palamaneru 2015-16 SCSP 50.96 37.22 1 0 0 0 0 0 0 7 15 9 35.96 16 50.96 8 34.96 Remaining Works under Progress
Chittoor 126 Palamaneru 2015-16 TSP 0.4 0.4 0.4 0 0 0 0 0 0 0 0 2 0.4 2 0.4 0 0 -
Chittoor 127 Palamaneru 2016-17 SCSP 125 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 128 Palamaneru 2016-17 TSP 62 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 129 Punganur 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 130 Punganur 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 131 Punganur 2014-15 SCSP 5.37 5.37 5.37 0 0 0 0 0 0 0 0 5 5.37 5 5.37 0 0 -
Chittoor 132 Punganur 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 133 Punganur 2015-16 SCSP 1.07 1.07 0 0 0 1 1.07 0 0 0 0 0 0 1 1.07 0 0 Tenders Completed and subject placed before council for tender acceptance
Chittoor 134 Punganur 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 135 Punganur 2016-17 SCSP 301 74.5 0 20 199 0 0 0 0 12 98 1 4 33 301 1 3.845 Bill Submitted to PAO, Chittoor on 15.02.2017
Chittoor 136 Punganur 2016-17 TSP 74 0 0 0 0 22 74 0 0 0 0 0 0 22 74 0 0 Tender files for 14 works sent to E.E.(P.H) Tirupati for Tender Opinion
Chittoor 137 Puttur 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 138 Puttur 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 139 Puttur 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 140 Puttur 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 141 Puttur 2015-16 SCSP 212.01 154.85 0 5 46 5 40 0 0 16 82.51 7 43.5 33 212.01 7 43.5 5 WORKS UNDER TENDER OPINION, 5 WORKS GRANT TO BE RELEASED. 16 WORKS IN PROGRESS, 7 WORKS COMPLETED & BILLS UNDER PREPARATION AND UNDER CURING.
Chittoor 142 Puttur 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 143 Puttur 2016-17 SCSP 419 0 0 36 419 0 0 0 0 0 0 0 0 36 419 0 0 COUNCIL RESOLUTION No.153, Dt:03-02-2017.
Chittoor 144 Puttur 2016-17 TSP 318 0 0 22 318 0 0 0 0 0 0 0 0 22 318 0 0 RESOLUTION No.154, Dt:03-02-2017.
Chittoor 145 Srikalahasti 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 146 Srikalahasti 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 147 Srikalahasti 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 148 Srikalahasti 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 149 Srikalahasti 2015-16 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 150 Srikalahasti 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 151 Srikalahasti 2016-17 SCSP 194 142.17 0 28 194 0 0 0 0 0 0 0 0 28 194 0 0 AS Completed and awaiting for TS
Chittoor 152 Srikalahasti 2016-17 TSP 164 0 0 25 164 0 0 0 0 0 0 0 0 25 164 0 0 AS Completed and awaiting for TS
Chittoor 153 Tirupati M.Corp 2013-14 SCSP 144.55 144.55 144.55 0 0 0 0 0 0 0 0 18 144.55 18 144.55 0 0 -
Chittoor 154 Tirupati M.Corp 2013-14 TSP 23.03 23.03 23.03 0 0 0 0 0 0 0 0 4 23.03 4 23.03 0 0 -
Chittoor 155 Tirupati M.Corp 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 156 Tirupati M.Corp 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Chittoor 157 Tirupati M.Corp 2015-16 SCSP 1570.6 1362.5 0 0 0 5 186.7 0 0 50 692.6 45 653.45 100 1532.75 45 653.45 Works are completed recently.Bills not paid
Chittoor 158 Tirupati M.Corp 2015-16 TSP 19.2 19.2 19.2 0 0 0 0 0 0 2 19.2 0 0 2 19.2 0 0 -
Chittoor 159 Tirupati M.Corp 2016-17 SCSP 5000 0 0 73 3455.85 0 0 0 0 0 0 0 0 73 3455.85 0 0 Proposals are submitted to Council for approval-
Chittoor 160 Tirupati M.Corp 2016-17 TSP 10 0 0 9 269.3 0 0 0 0 0 0 0 0 9 269.3 0 0 Proposals are submitted to Council for approval-
East Godavari 161 Amalapuram 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 162 Amalapuram 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 163 Amalapuram 2014-15 SCSP 21.83 0 21.83 0 0 0 0 0 0 0 0 5 21.83 5 21.83 0 0 All works Completed from Municipal General funds, Grant Not released. -
East Godavari 164 Amalapuram 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 165 Amalapuram 2015-16 SCSP 122.08 89.17 0 3 37 0 0 0 0 11 81 1 4.08 15 122.08 0 0 Out of 15 No.s works, 12 No. works tenders called and work order issued . For remaining 3 works estimates preparation is held up due to not finalisation of site and building plans by Town Planning section.
East Godavari 166 Amalapuram 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 167 Amalapuram 2016-17 SCSP 331.5 0 0 0 0 34 331.5 0 0 0 0 0 0 34 331.5 0 0 out of 34 works, 13 works Tender called and to be open on 28.02.2017 and 21 works tenders to be called after election code
East Godavari 168 Amalapuram 2016-17 TSP 30 0 0 0 0 3 30 0 0 0 0 0 0 3 30 0 0 Tenders to be lopen on 28.02.2017
East Godavari 169 Gollaprolu 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 170 Gollaprolu 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 171 Gollaprolu 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 172 Gollaprolu 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 173 Gollaprolu 2015-16 SCSP 56.93 41.58 0 2 47 0 0 0 0 2 8.94 1 0.99 5 56.93 1 0.71 1. Construction of Community Hall with an estimated cost Rs.13.00 lakhs was Resubmitted for building plan approval to RJDTP, Rajamahendravaram. 2. Construction of Storm water drain along railway track with an estimated cost Rs.34.00 lakhs for tender received on 27-02-2017.
East Godavari 174 Gollaprolu 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 175 Gollaprolu 2016-17 SCSP 100 0 0 6 100 0 0 0 0 0 0 0 0 6 100 0 0 Administrative sanctioned wide CR No.628, Dated 31-01-2017
East Godavari 176 Gollaprolu 2016-17 TSP 80 0 0 4 80 0 0 0 0 0 0 0 0 4 80 0 0 Administrative sanctioned wide CR No.629, Dated 31-01-2017
East Godavari 177 Kakinada M.Corp 2013-14 SCSP 286.18 240.4 171.67 0 0 0 0 0 0 0 0 37 286.18 37 286.18 0 0 -
East Godavari 178 Kakinada M.Corp 2013-14 TSP 2.13 1.18 0.84 0 0 0 0 0 0 0 0 1 1.18 1 1.18 0 0 -
East Godavari 179 Kakinada M.Corp 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 180 Kakinada M.Corp 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 181 Kakinada M.Corp 2015-16 SCSP 1258.29 1076.26 230.25 0 0 3 210 0 0 13 433.25 28 527.81 44 1171.06 0 0 4 works cancelled Rs.39.62 lakhs-
East Godavari 182 Kakinada M.Corp 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 183 Kakinada M.Corp 2016-17 SCSP 4000 0 0 0 0 21 1852.9 0 0 76 1909.54 0 0 97 3762.44 0 0 1work cancelled Rs.25.00 lakhs-
East Godavari 184 Kakinada M.Corp 2016-17 TSP 1000 35.5 0 1 20 1 5.5 0 0 1 10 0 0 3 35.5 0 0 -
East Godavari 185 Mandapeta 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 186 Mandapeta 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 187 Mandapeta 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 188 Mandapeta 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 189 Mandapeta 2015-16 SCSP 24.67 18.02 0 0 0 0 0 0 0 0 0 3 29.95 3 29.95 0 0 All works completed.
East Godavari 190 Mandapeta 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 191 Mandapeta 2016-17 SCSP 633.09 633.09 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Estimates are submitted for technical sanction for Rs.633.09 lakhs on 14.2.2017 .
East Godavari 192 Mandapeta 2016-17 TSP 66.1 66.1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Estimates are submitted for technical sanction for Rs. 66.10 lakhs on 14.2.2017.
East Godavari 193 Mumidivaram 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 194 Mumidivaram 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 195 Mumidivaram 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 196 Mumidivaram 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 197 Mumidivaram 2015-16 SCSP 104.18 76.09 12.05 0 0 12 88.34 0 0 2 18.58 2 10.5 16 117.42 0 0 -
East Godavari 198 Mumidivaram 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 199 Mumidivaram 2016-17 SCSP 100 0 0 16 178 0 0 0 0 0 0 0 0 16 178 0 0 -
East Godavari 200 Mumidivaram 2016-17 TSP 25 0 0 2 25 0 0 0 0 0 0 0 0 2 25 0 0 -
East Godavari 201 Peddapuram 2013-14 SCSP 26.48 26.48 22.06 0 0 0 0 0 0 0 0 5 22.06 5 22.06 0 0 -
East Godavari 202 Peddapuram 2013-14 TSP 0.55 0.55 0.55 0 0 0 0 0 0 0 0 1 0.55 1 0.55 0 0 -
East Godavari 203 Peddapuram 2014-15 SCSP 4.81 4.81 4.81 0 0 0 0 0 0 0 0 1 4.81 1 4.81 0 0 -
East Godavari 204 Peddapuram 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 205 Peddapuram 2015-16 SCSP 59.02 43.11 0 0 0 2 11.63 1 5.6 2 52.6 2 1.15 7 70.98 0 0 Presented 2 Bills to APAO, Kakinada for making payment
East Godavari 206 Peddapuram 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 207 Peddapuram 2016-17 SCSP 300 0 0 0 0 13 300 0 0 0 0 0 0 13 300 0 0 6 Nos of Works tenders opening on 18.02.2017 , 6 Nos of Work tenders opening on 27.02.2017 & One work is Nit Permision obtained from ENC (PH)on 15.02.2017, The above tenders (on18.02.2017 ) not opened due to election code,and one work tender are not called due to election code.
East Godavari 208 Peddapuram 2016-17 TSP 7 0 0 0 0 1 7.55 0 0 0 0 0 0 1 7.55 0 0 1 No of Work tender opening on 18.02.2017 (on18.02.2017 ) not opened due to election code,and one work tender are not opened due to election code.
East Godavari 209 Pithapuram 2013-14 SCSP 92.8 92.8 92.8 0 0 0 0 0 0 0 0 20 92.8 20 92.8 0 0 -
East Godavari 210 Pithapuram 2013-14 TSP 0.59 0.59 0.59 0 0 0 0 0 0 0 0 2 0.59 2 0.59 0 0 -
East Godavari 211 Pithapuram 2014-15 SCSP 8.11 8.11 8.11 0 0 0 0 0 0 0 0 5 8.11 5 8.11 0 0 -
East Godavari 212 Pithapuram 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 213 Pithapuram 2015-16 SCSP 272.42 198.98 1.02 0 0 17 161.56 0 0 5 37.42 0 0 22 198.98 0 0 5 Works to be completed by 28-02-2017. 11 works under tender process. In which, 2 works of 35.00 Lakhs under finalization. Remaining 15 works of 90.00 Lakhs opened by 25-02-2017.
East Godavari 214 Pithapuram 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 215 Pithapuram 2016-17 SCSP 502 0 0 18 256 0 0 0 0 0 0 0 0 18 256 0 0 -
East Godavari 216 Pithapuram 2016-17 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 217 Rajahmundry M.Corp 2013-14 SCSP 353.42 353.42 147.95 0 0 0 0 0 0 0 0 27 147.95 27 147.95 0 0 -
East Godavari 218 Rajahmundry M.Corp 2013-14 TSP 2.55 2.55 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 219 Rajahmundry M.Corp 2014-15 SCSP 33.51 33.51 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Proposals are under finalisation -
East Godavari 220 Rajahmundry M.Corp 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 221 Rajahmundry M.Corp 2015-16 SCSP 56.93 41.58 0 0 0 0 0 0 0 8 54.74 1 6 9 60.74 1 6 Works under excution -
East Godavari 222 Rajahmundry M.Corp 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 223 Rajahmundry M.Corp 2016-17 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 224 Rajahmundry M.Corp 2016-17 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 225 Ramachandrapuram 2013-14 SCSP 64.04 64.04 64.04 0 0 0 0 1 3 1 5 11 56.04 13 64.04 0 0 One work will be completed on 28-02-2017
East Godavari 226 Ramachandrapuram 2013-14 TSP 0.6 0.6 0.6 0 0 0 0 0 0 1 0.6 0 0 1 0.6 0 0 One work will be completed on 28-02-2017-
East Godavari 227 Ramachandrapuram 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 228 Ramachandrapuram 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 229 Ramachandrapuram 2015-16 SCSP 42.51 31.09 15 0 0 0 0 4 11.46 5 15.84 3 15 12 42.3 0 0 9 works will be completed on 31-03-2017
East Godavari 230 Ramachandrapuram 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 231 Ramachandrapuram 2016-17 SCSP 280 0 0 0 0 23 225 0 0 7 35 0 0 30 260 0 0 Estimates to be submitted for technical sanction-
East Godavari 232 Ramachandrapuram 2016-17 TSP 61 0 0 0 0 5 46 0 0 3 15 0 0 8 61 0 0 Estimates to be submitted for technical sanction--
East Godavari 233 Samalkota 2013-14 SCSP 109.35 94.81 60.88 0 0 0 0 1 10 0 0 13 60.12 14 70.12 0 0 -Works Completed Deviation Statements under Preparation.
East Godavari 234 Samalkota 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 235 Samalkota 2014-15 SCSP 10.2 10.2 9.12 0 0 0 0 0 0 0 0 2 7.51 2 7.51 0 0 -
East Godavari 236 Samalkota 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 237 Samalkota 2015-16 SCSP 364.08 265.93 0 1 8.2 23 148.16 19 173.22 4 34.5 0 0 47 364.08 0 0 4nos of works grounded. 19Nos of works will be grounded by the end of this week. -
East Godavari 238 Samalkota 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 239 Samalkota 2016-17 SCSP 300 0 0 19 300 0 0 0 0 0 0 0 0 19 300 0 0 Estimates under preparation -
East Godavari 240 Samalkota 2016-17 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 241 Tuni 2013-14 SCSP 98.04 74.38 75.11 0 0 0 0 0 0 0 0 9 75.11 9 75.11 0 0 -
East Godavari 242 Tuni 2013-14 TSP 0.58 0.44 0.5 0 0 0 0 0 0 0 0 3 0.5 3 0.5 0 0 -
East Godavari 243 Tuni 2014-15 SCSP 29.73 5.2 9.12 0 0 0 0 0 0 1 5.2 0 0 1 5.2 0 0 -
East Godavari 244 Tuni 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 245 Tuni 2015-16 SCSP 110.34 80.6 0 0 0 1 20 0 0 10 90.34 0 0 11 110.34 0 0 -
East Godavari 246 Tuni 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 247 Tuni 2016-17 SCSP 65 0 0 3 65 0 0 0 0 0 0 0 0 3 65 0 0 -
East Godavari 248 Tuni 2016-17 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 249 Yeleswaram 2013-14 SCSP 55.07 55.07 53 0 0 0 0 0 0 0 0 9 53 9 53 0 0 -
East Godavari 250 Yeleswaram 2013-14 TSP 1.17 1.17 0.85 0 0 0 0 0 0 0 0 1 0.85 1 0.85 0 0 -
East Godavari 251 Yeleswaram 2014-15 SCSP 43.02 43.02 38 0 0 0 0 0 0 0 0 11 38 11 38 0 0 -
East Godavari 252 Yeleswaram 2014-15 TSP 2 2 1.65 0 0 0 0 0 0 0 0 1 1.65 1 1.65 0 0 -
East Godavari 253 Yeleswaram 2015-16 SCSP 132.35 95.79 0 8 35.8 0 0 0 0 12 33.95 0 0 20 69.75 0 0 -Balance amount works estimates has to be prepared
East Godavari 254 Yeleswaram 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
East Godavari 255 Yeleswaram 2016-17 SCSP 100 0 0 28 118 0 0 0 0 0 0 0 0 28 118 0 0 -Estimates to be prepared
East Godavari 256 Yeleswaram 2016-17 TSP 121 0 0 22 121 0 0 0 0 0 0 0 0 22 121 0 0 Estimates to be prepared -
Guntur 257 Bapatla 2013-14 SCSP 96.34 96.34 84.34 0 0 0 0 2 12 0 0 18 84.34 20 96.34 0 0 Encroachment problem for road widening in GBC Road.
Guntur 258 Bapatla 2013-14 TSP 4.5 4.5 4.5 0 0 0 0 0 0 0 0 4 4.5 4 4.5 0 0 -
Guntur 259 Bapatla 2014-15 SCSP 8.75 8.75 8.75 0 0 0 0 0 0 0 0 2 8.75 2 8.75 0 0 -
Guntur 260 Bapatla 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 261 Bapatla 2015-16 SCSP 91.15 66.58 0 0 0 0 0 1 4.2 1 85 2 1.95 4 91.15 1 85 850 KL ELSR Under Progress.20% Work is completed.
Guntur 262 Bapatla 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 263 Bapatla 2016-17 SCSP 52 0 0 0 0 2 21 9 31 0 0 0 0 11 52 0 0 -
Guntur 264 Bapatla 2016-17 TSP 2 0 0 0 0 0 0 1 2 0 0 0 0 1 2 0 0 -
Guntur 265 Chilakaluripet 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 266 Chilakaluripet 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 267 Chilakaluripet 2014-15 SCSP 55.51 55.51 55.51 0 0 0 0 0 0 0 0 7 55.51 7 55.51 0 0 -
Guntur 268 Chilakaluripet 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 269 Chilakaluripet 2015-16 SCSP 49 35.79 0 0 0 0 0 0 0 0 0 5 49 5 49 5 49 Bill process-
Guntur 270 Chilakaluripet 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 271 Chilakaluripet 2016-17 SCSP 2604 0 0 113 1912.7 21 742.6 0 0 0 0 0 0 134 2655.3 0 0 Administrative Sanction accorded by DMA, Guntur with an amount Rs.2604.00 lakhs 21 works are tender stage and remaining works are TS stage. 51.30 lakhs are ULB Funds
Guntur 272 Chilakaluripet 2016-17 TSP 328 0 0 4 108 9 257.2 0 0 0 0 0 0 13 365.2 0 0 9 works are tender stage and remaining 4 works are are TS stage
Guntur 273 Guntur M.Corp 2013-14 SCSP 516.37 0 460.07 0 0 0 0 0 0 0 0 58 460.07 58 460.07 0 0 -
Guntur 274 Guntur M.Corp 2013-14 TSP 169.25 0 16.25 0 0 0 0 0 0 0 0 10 16.25 10 16.25 0 0 -
Guntur 275 Guntur M.Corp 2014-15 SCSP 228.43 0 217.08 0 0 0 0 0 0 0 0 30 217.08 30 217.08 0 0 -
Guntur 276 Guntur M.Corp 2014-15 TSP 292.35 0 292.35 0 0 0 0 0 0 0 0 19 292.35 19 292.35 0 0 -
Guntur 277 Guntur M.Corp 2015-16 SCSP 5000 4337.51 121 25 1003 26 920 35 985 45 1529 34 515 165 4952 22 345 "Tender Stage - 35 works - 1244.00 Lakhs Work in Progress - 25 - 895.47 Work to Started - 48- 1436.07 Lakhs" -
Guntur 278 Guntur M.Corp 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 279 Guntur M.Corp 2016-17 SCSP 6000 0 0 35 1056.36 0 0 0 0 0 0 0 0 35 1056.36 0 0 Estimates under Preaparation -
Guntur 280 Guntur M.Corp 2016-17 TSP 2000 0 0 76 2143.86 0 0 0 0 0 0 0 0 76 2143.86 0 0 Estimates under Preaparation -
Guntur 281 Macherla 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 282 Macherla 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 283 Macherla 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 284 Macherla 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 285 Macherla 2015-16 SCSP 44.91 32.8 0 4 11.29 3 6.17 0 0 3 15.45 4 12 14 44.91 0 0 work is under progress.
Guntur 286 Macherla 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 287 Macherla 2016-17 SCSP 467 0 0 13 71.87 15 361.63 0 0 8 33.5 0 0 36 467 0 0 -
Guntur 288 Macherla 2016-17 TSP 165.1 0 0 1 8 6 157.1 0 0 0 0 0 0 7 165.1 0 0 -
Guntur 289 Mangalagiri 2013-14 SCSP 73.67 55.63 55.63 0 0 0 0 0 0 0 0 39 60.93 39 60.93 0 0 -
Guntur 290 Mangalagiri 2013-14 TSP 2.43 1.86 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 291 Mangalagiri 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 292 Mangalagiri 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 293 Mangalagiri 2015-16 SCSP 96.57 70.53 0 0 0 0 0 18 50.79 8 32.33 5 21.28 31 104.4 2 7.9 -
Guntur 294 Mangalagiri 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 295 Mangalagiri 2016-17 SCSP 200 0 0 0 0 14 176 11 29 4 21.2 2 4.8 31 231 0 0 --
Guntur 296 Mangalagiri 2016-17 TSP 69 0 0 11 65 0 0 0 0 1 4 0 0 12 69 0 0 --
Guntur 297 Narasaraopeta 2013-14 SCSP 46 46 26 0 0 0 0 2 15 1 5 1 26 4 46 0 0 All the works are cancelled with council approval. Since contractors are not came forward because grant is not released. Tenders are recalled for the same works after grant -
Guntur 298 Narasaraopeta 2013-14 TSP 3.29 3.29 0 0 0 0 0 0 0 2 3.29 0 0 2 3.29 0 0 All the works are cancelled with council approval. Since contractors are not came forward because grant is not released. Tenders are recalled for the same works after grant -
Guntur 299 Narasaraopeta 2014-15 SCSP 17.5 17.5 0 0 0 0 0 4 14 0 0 1 3.5 5 17.5 0 0 All the works are cancelled with council approval. Since contractors are not came forward because grant is not released. Tenders are recalled for the same works after grant -
Guntur 300 Narasaraopeta 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 301 Narasaraopeta 2015-16 SCSP 40.17 29.34 0 0 0 0 0 8 40.17 0 0 0 0 8 40.17 0 0 Tenders are called, LOA is issued and work in progress.
Guntur 302 Narasaraopeta 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 303 Narasaraopeta 2016-17 SCSP 213 0 0 5 107 17 106 0 0 0 0 0 0 22 213 0 0 5 works are sent to S.E. PH for T.S. 17 works are Tender in progress
Guntur 304 Narasaraopeta 2016-17 TSP 15 0 0 0 0 3 15 0 0 0 0 0 0 3 15 0 0 Tenders in progress
Guntur 305 Piduguralla 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 306 Piduguralla 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 307 Piduguralla 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 308 Piduguralla 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 309 Piduguralla 2015-16 SCSP 29.58 21.6 21.29 0 0 0 0 2 3.8 0 0 6 25.78 8 29.58 1 6.77 BALANCE AMOUNT TO BE RELEASED -
Guntur 310 Piduguralla 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 311 Piduguralla 2016-17 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 312 Piduguralla 2016-17 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 313 Ponnur 2013-14 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 314 Ponnur 2013-14 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 315 Ponnur 2014-15 SCSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 316 Ponnur 2014-15 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 317 Ponnur 2015-16 SCSP 168.26 122.9 0 3 23.46 1 6 10 80.3 6 42.5 2 16 22 168.26 0 0 2 WORKS COMPLETED 6 works is in progress. Further 10 works to be started and tender is called for 3rd time. 2 work ie., water supply pipe line estimates are under finalisation and one work ie., Electrical work amount will be paid to the APSPDCL
Guntur 318 Ponnur 2015-16 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 319 Ponnur 2016-17 SCSP 700 0 0 1 700 0 0 0 0 0 0 0 0 1 700 0 0 The Estimate submitted to Superintending Engineer (PH) QCC Guntur through Executive Engineer (PH) Guntur. Duly obtaining the Administrative Inancipation orders of Chair Person and more over the action also ratified by the Municipal Council on 31-01-2017. The Estimation is under finalised at Superintending Engineer (PH) QCC, Guntur.
Guntur 320 Ponnur 2016-17 TSP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -
Guntur 321 Repalle 2013-14 SCSP 55.78 55.78 27.77 0 0 1 17.81 0 0 2 10 5 27.97